Building Construction Timeline
|
2003 November |
Executed contract, obtained building permit, prepared site, demolished
brick classroom building (Nov. 25-26). Grading. |
|
|
December |
Laid forms, roughed-in plumbing and electrical, poured slab,
framed 1st, created floor system.
|
|
|
2004 January |
2nd fl. & interior framing, set trusses, roofing, plumbing
rough, shingles, electrical/HVAC rough, fir ceilings. “Dried in” goal reached 23Jan04. |
|
|
February |
Insulation, drywall, masonry, deck footings, external
decks, doors & trim, texture ceilings.
|
|
|
March |
Exterior concrete, paint & stain, set cabinets, cedar shakes (porch)*, electrical & mechanical trim, hardware
& fixtures, ceramic flooring.
Soffits frames
in meeting room.* Grading. |
|
|
April |
Site cleanup.
Dodson-Chatman completes project by 4/9.
Hardwood
flooring* 4/12-19.
Landscaping
(including plantings required by the City)*. Flooring*.
|
|
|
May |
Floor sanding and finishing (5/11).
Passed inspections: Landscaping, Building. |
|
|
June |
Passed inspections: Fire marshall.
Installed new fire hydrant. Complete punch-list. 23rd:
Obtained certificate of occupancy. Final cleaning. First
event held in new building on 7th of July. |
|
* Tasks
completed by teams of volunteers from the meeting.
Last updated 22 June 2004.